bazzard | 11:39 Thu 22nd Nov 2018 | Law
3 Answers
Planning permission granted for a house extension in June 2016. How long is it valid for, or is there no set rule?
Gravatar

Answers

1 to 3 of 3rss feed

Best Answer

No best answer has yet been selected by bazzard. Once a best answer has been selected, it will be shown here.

For more on marking an answer as the "Best Answer", please visit our FAQ.
Unless there are stipulations to the contrary, development should begin within 3 years of the date that permission is granted.

https://www.designingbuildings.co.uk/wiki/How_long_does_planning_permission_last
Three years from permission being granted unless work has started. If any work has been done to start the project, even just the start of foundations, then there is usually no time limit unless there is a stipulation in the PP. You can access PP for any property online if you have the full postal code and address.
Question Author
Nice clear answers, thank you