We are having our kitchen revamped i.e. units sprayed. We are also putting down new flooring and although we are having the units sprayed we are also having some new end panels.
A company is spraying the units but hubby is laying a new floor (vinyl laminate boards). Are we best laying the floor first?
We've recently done the same and the kitchen fitters said the units had to sit on hard floor not laminate tiles, the floor can be fitted afer all the work is done to just under the units
If your kitchen units are not being removed and replaced, then I would think it best to lay the floor after the spraying, so you don't risk spray marking the new floor.